Articles by Topic Area
Articles by Publication
|
Salvaging Unfinished Projects in the Current Credit Market
Each party, whether a tapped-out developer or under-secured lenders or unpaid contractors and consultants, has a stake in the project, the value of which diminishes as the parties dispute the issues. Each party can protect and even enhance its stake by cooperating with the others to maximize the property's value and to minimize avoidable dispute costs. What follows are the steps that must occur to achieve the best outcome possible.
A bank may have the right and power to refuse to advance funds, but if doing so converts a 90 percent product into a delayed project worth 70 percent of what was invested, exercising that right will put the bank further behind. Similarly, the contractor or owner may have to forgo some or all of its profit to finish, but by doing so it may recover its costs and keep its subcontractor relationships. All parties can enhance their returns by avoiding litigation costs. How can this actually play out? Here is a recent case history. The project was 90 percent complete, but the expected cost to finish would substantially exceed the original budgets. The owner's resources were depleted, credit limits were maxed out, and the contractor was owed a substantial sum. The lender suspended funding, the owner stopped work, and the contractor filed its lien. But the contractor chose not to immediately exercise its right to terminate the contract and foreclose its lien, leaving room for all parties to maneuver. After multiparty, multiangle discussions, the ultimate resolution was a change order to the contract that ultimately led to completion. The contractor received more than 90 percent of its lien claim but agreed to an absolute maximum fixed cost to finish the work. The lender agreed to fund the final work, given the limit, and received an additional supplemental guarantee for payment from the investors and the owner. A short-term completion schedule was agreed to by all parties. At the end of the day every party gave up something, but no party was forced to bear the total burden or expense of the problem, and the project was then completed. That is obviously the ultimate goal of any construction project and should remain the goal even when problems develop. Published Summer 2008 This article is intended to inform the reader of general legal principles applicable to the subject area. It is not intended to provide legal advice regarding specific problems or circumstances. Readers should consult with competent counsel with regard to specific situations. |
||||||
|
Copyright © 2010 by Jordan Schrader Ramis PC. All rights reserved.
|
|||||||



What happens when a development project runs out of money before the work is done? Today's tight credit and uncertain market prospects put a shadow of risk over once-promising projects. As the expectation of profitability dwindles, even the smallest delay or unanticipated expense can upset a precarious balance and the work can grind to a halt.